Cracks were found on the surfaces of the existing pile caps supporting the elevated railway near Yio Chu Kang MRT station (NS15). The observation was during the excavation work for a North-South Corridor (NSC) contract. The main contractor approached Fibrwrap Construction Pte Ltd for the rectification of pile caps.
The TYFO® Fibwrap® System was recommended and approved for the repair. The existing cracks were initially repaired by injecting epoxy. The TYFO® Fibwrap® System was installed following the repair of cracks. The TYFO® Fibwrap® System served as externally bonded reinforcement upon the repair of cracks, providing additional protection against water ingress.
Overall, the project was completed to the satisfaction of all parties.